Hope everyone had a Great
Thanksgiving. Back to work on the
House.
11/24/06 windows
installed -Insulation is three quarters installed. All the
soffits are installed as are the ceilings for the entrance way and
the covered porch. The exterior doors are due in on the 28th and the
Large front door is due Dec. 5th 2006
Covered porch
with windows. We will start the Drywall process next
week . The door did not make it on the 5th but was delivered on
the 8th of December. Pictures were taken on
12/13/2006
The following pictures are of the front
entrance with the Pillars framed in and the front door installed.
Also of the Sitting Room drywalled and with the covered porch with
the posts and door installed, still waiting on the other door and
window. Also during the process a Canine decided to adopt the
home and become its guard dog. How this happened???????? Anyway we
will try to find the owners.

House to have the drywall completed
including the tape and float and texture by December
17th 2006. The interior will be painted at this time before the
Electricians come out to do the final installation of the fixtures
and the plumbing will be completed as well as also the
HVAC.
|